Latest SAP C_P2W22_2504 Exam questions and answers [Q22-Q42]

Share

Latest SAP C_P2W22_2504 Exam questions and answers

Exam-Killer C_P2W22_2504 Exam Practice Test Questions (Updated 82 Questions)

NEW QUESTION # 22
What is the focus of repetitive manufacturing?

  • A. Detailed tracking of production orders
  • B. Period and quantity-oriented production
  • C. Production of lot size one
  • D. Low volume production

Answer: B


NEW QUESTION # 23
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?

  • A. Sequencing on multi-activity resources is automatically updated during planning.
  • B. An operation is scheduled as close as possible to the desired date.
  • C. To create a slot, neighbouring operations are moved in both planning directions.
  • D. Operations on multi-resources are planned finitely in a sequence.

Answer: B


NEW QUESTION # 24
Which operations are considered in the capacity scheduling table?
Note: There are 2 correct answers to this question.

  • A. Operations assigned to a pacemaker work center
  • B. Sub-operations
  • C. All operations
  • D. Only bottleneck operations

Answer: B,D


NEW QUESTION # 25
You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?

  • A. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Individual/Collective indicator
  • B. Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator
  • C. Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator
  • D. Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator

Answer: C


NEW QUESTION # 26
What are some benefits of planning with planned independent requirements for finished materials?
Note: There are 2 correct answers to this question.

  • A. You have the option to use forecast planning.
  • B. The delivery time is reduced.
  • C. You have the option to use make-to-order production.
  • D. Manufacturing time for final assembly is reduced.

Answer: A,C


NEW QUESTION # 27
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

  • A. Assign the alert profile to the overall profile
  • B. Create an object selection variant for production-planning-related alerts
  • C. Assign the overall profile to the authorization profile
  • D. Create an object selection variant for alerts according to the priority of ATP categories

Answer: A,B


NEW QUESTION # 28
In the context of the capacity scheduling table, how do you define a pacemaker work center?

  • A. By assigning it to the capacity scheduling table
  • B. By assigning it to the production version
  • C. By assigning it to the bottleneck operation
  • D. By assigning it to the first operation of a routing

Answer: B


NEW QUESTION # 29
How would you define a pegging structure for an order in the context of Advanced Planning?

  • A. An evaluation that is ordered according to the low-level codes of all related products and represents the coverage of issue elements with receipt elements and stock
  • B. An evaluation to identify material or capacity shortages in the bill-of-material structure after the production planning run
  • C. An evaluation to identify overstock situations based on the assignment of receipt and issue elements after the production planning run
  • D. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between receipt and issue elements

Answer: D


NEW QUESTION # 30
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.

  • A. Default order types
  • B. Automatic print on order creation
  • C. Automatic release on order creation
  • D. Automatic goods receipt on confirmation
  • E. Automatic goods issue on confirmation

Answer: A,C,D


NEW QUESTION # 31
Which of the following would you recommend as SAP's strategic Sales and Operations planning tool?

  • A. Advanced Planning
  • B. Integrated Business Planning
  • C. Flexible Planning
  • D. Standard Sales and Operations Planning

Answer: B


NEW QUESTION # 32
What are the selection criteria of a bill of material (BOM) alternative?
Note: There are 2 correct answers to this question.

  • A. Lot size
  • B. Date
  • C. Change number
  • D. Material BOM usage

Answer: A,B


NEW QUESTION # 33
What data can you maintain in the items detail screen of a bill of material (BOM)?
Note: There are 2 correct answers to this question.

  • A. Alternative item group
  • B. Change number
  • C. Lot size
  • D. Co-product

Answer: A,D


NEW QUESTION # 34
In SAP documentation for MRP in Advanced Planning, you read that the MRP creates new planned orders through infinite scheduling. What does this mean for the capacity requirements of the new planned order?

  • A. MRP automatically assigns the capacity requirements to resources with the earliest available capacity.
  • B. MRP automatically assigns the capacity requirements after the last scheduled operation for each resource.
  • C. MRP creates the capacity requirements on resources at the earliest possible production time.
  • D. MRP creates the capacity requirements without considering existing load on the resources.

Answer: D


NEW QUESTION # 35
What does Consumption-based Planning use to determine requirements in the future?
Note: There are 3 correct answers to this question.

  • A. Forecasting
  • B. Planning file entries
  • C. Historical values
  • D. Statistical procedures
  • E. Dependent requirements

Answer: A,C,D


NEW QUESTION # 36
Which options do you have to exclude Advanced Planning materials from the standard MRP run in SAP S/4HANA?
Note: There are 2 correct answers to this question.

  • A. Use the special MRP type XO
  • B. Use the material number for selection
  • C. Use a different MRP planner for PP/DS materials
  • D. Use a propagation range

Answer: A,C


NEW QUESTION # 37
Which of the following are scheduling time elements for a production order?
Note: There are 3 correct answers to this question.

  • A. Setup time
  • B. Float before production
  • C. Queue time
  • D. Load time
  • E. Transit time

Answer: A,B,C


NEW QUESTION # 38
Which of the following processes lead to an indicator in the planning file?
Note: There are 2 correct answers to this question.

  • A. Changing an operation time
  • B. Changing a dependent requirement
  • C. Changing a storage bin
  • D. Changing a delivery address

Answer: A,B


NEW QUESTION # 39
How do you assign resources in a master recipe with operations and phases?

  • A. You assign resources to the operations.
  • B. You assign resources to the phases.
  • C. You assign resources to the header of the master recipe.
  • D. You assign resources to the sub-operations.

Answer: A


NEW QUESTION # 40
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.

  • A. Material type
  • B. MRP type
  • C. MRP group
  • D. Procurement type

Answer: B,D


NEW QUESTION # 41
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. For which plant can the BOM be defined?
  • B. In which storage location is the BOM required?
  • C. Which base unit of measure must the BOM have?
  • D. When does the BOM need to become effective?

Answer: A,D


NEW QUESTION # 42
......

Pass Your SAP Exam with C_P2W22_2504 Exam Dumps: https://www.exam-killer.com/C_P2W22_2504-valid-questions.html

Pass C_P2W22_2504 Exam Info and Free Practice Test: https://drive.google.com/open?id=1XvN0xz8kqF0nBCcy8oNQLYan9byrEpg8